Clay Electric customers in Orange Park to get new advanced meters

New upgraded meters to improve reliability, efficiency, reduce outages

No description found

ORANGE PARK, Fla. – Clay Electric customers in Orange Park will get new meters installed next month.

The utility company hired contractors to change out existing meters with advanced meters beginning in January.

Recommended Videos



Customers will get a notification by mail to know when their meter will be replaced. Power will be out for a few minutes during the installation. Utility users will get a door hanger notifying them when it's been replaced.

Contractors will be in uniform and wear identification. They will not enter any home or ask for personal information or payment. 

Clay Electric officials said the upgrade will:

  • Improve reliability by identifying and pinpointing outages more quickly.
  • Improve member service by providing detailed data about energy use in the home and business.
  • Improve efficiency in managing operational costs with remote meter reading, saving money by significantly reducing labor and transportation costs. 

Click here for more information about the meter upgrade project.

Below is the meter deployment schedule.

                District                                                                  Estimated time frame              

Orange ParkJan.-Sept. 2019
PalatkaSept.-Oct. 2019
Salt SpringsOct.-Dec.2019
Keystone HeightsDec.2019- Feb. 2020
GainesvilleFeb.-April 2020
Lake CityApril-June 2020

 